08-21 ~ 08-27
Finance estimation of cash-flow until 09-30 - done
Participants additional approval - done
Program decide meeting room facilities - done
decide on breakfast management - done
Documents participant list - basic revision - done
Meetings management meeting (08-22, 08-23, 08-24, 08-26) - done
08-28 ~ 09-03
Finance 2nd DotAsia payment - done
Participants close participant list (except local participants) - done
Program finalize the opening session plan - done
finalize the video recording plan - done
decide dinner place - done
welcome package - finalize - done
Documents participant list - basic - done
participant list - payment - done
managerial budget - final - done
Meetings management meeting (08-29, 08-31, 09-02) - done
APSIG monthly remote meeting on 09-01 - done
09-04 ~ 09-10
Finance status report - done
cashing (for payment and urgent expense) - done
last DotAsia payment - done
Program remote participation - final plan - done
Documents evaluation form - done
participant lists - done
Meetings management meeting (daily: 09-05 ~ 09-09) - done
09-11 ~ 09-17
Participants payment to participants - done
hotel payment (guest room, breakfast) - done
settlement with AIT - done
Documents participant list - role play - done
Meetings daily management meetings (07:00 / right after dinner) - done
09-18 ~ 09-24
Documents APSIG settlement (2016-01-01 ~ 09-30) - draft - done
09-25 ~ 10-01
Documents APSIG 2016 report - draft - done